Chris,
On the Flexy 205, the time and date is displayed MM/DD/YYYY. This also applies to data logging. Is it possible to change the to US display? MM/DD/YYYY?
James M. Belcher
Senior Controls Engineer
Chris,
On the Flexy 205, the time and date is displayed MM/DD/YYYY. This also applies to data logging. Is it possible to change the to US display? MM/DD/YYYY?
James M. Belcher
Senior Controls Engineer
Hi James,
This is something that’s possible but it’s a little complicated. I have some code written up that basically will create some custom historical log in a CSV file where you can choose how you want the date displayed below.
New Historical Logging.txt (2.2 KB)
The way that this one worked was it would write everytime that a certain cycle changed but we should be able to modify it for what you want to do